Insights ยท Election technology
Election results transmission: the tests to witness before acceptance
A results system is judged on one night, by people who did not build it and do not trust it. The time to find out how it behaves is before acceptance, in tests the commission watches for itself.
On results night, three things arrive at once. Thousands of polling stations send their figures within the same few hours. Some of them do so over links that drop in and out. And every party, observer and journalist is watching for a reason to doubt what appears on the screen.
A system that has only been tested in the supplier’s laboratory has not been tested against any of this. Acceptance testing is where an election commission turns a supplier’s claims into evidence it can defend in public. Six tests matter most.
1. Load at several times the expected peak
Work out the busiest hour you expect: the number of polling stations, the share likely to report in that hour, and the size of each submission, including images of the signed result forms. Then ask the supplier to run the full system at three times that load, end to end, while you watch the dashboards.
Staying up is the first test. The second is whether it slows down gracefully. Submissions should queue and be processed in order, and a polling station that sends its results at the peak should see them confirmed within a time the commission has fixed in advance.
2. Several loads at the same time
Systems often pass each test separately and fail when the tests run together. On the night, results intake, the public results portal, the commission’s own dashboards and the media feeds all run at once. The acceptance test should run them at once too, with the public portal under heavy simulated traffic while results are flowing in.
The public portal should be separated from the tally, so that a surge of visitors cannot slow down the counting. The test is where that separation is proven.
3. Failure of a site, a link and a server
Ask the supplier to switch off one of the two data centers in the middle of a load test, then a network link, then a database server, and to show what happens. Results already received must not be lost. Results in transit must arrive once, and only once. The commission should know in advance how long recovery may take, and then measure it.
A disaster recovery plan that has never been run is a document. On results night, it needs to be a procedure that staff have already performed.
4. A polling station with no connection
Some stations will not be able to transmit at all. The devices there should store the results securely, keep trying, and send them when a connection returns, without the operator having to do anything unusual. Test it by disconnecting devices for several hours and reconnecting them at the busiest moment of a load test.
5. The paper trail matches the screen
In most systems the signed paper result form remains the legal record, and the electronic transmission is a faster copy of it. The commission should test that the two can always be matched: that every figure on the screen can be traced to an image of the signed form, and that any change after submission is recorded, with who made it and when.
One practical safeguard is to record a cryptographic fingerprint of every form image as it arrives and to publish those fingerprints. Anyone holding a copy of a form can then check that the image the commission received has not been altered since. This makes tampering detectable. Mistakes still need the reconciliation test.
6. Security tested by someone other than the builder
Penetration testing should be done by a firm independent of the supplier, with a scope agreed by the commission, and repeated after the fixes are made. The report should go to the commission directly. A supplier marking its own work cannot provide that assurance.
Write the tests into the contract
Each of these tests needs three things fixed before the contract is signed: a measurable pass mark, the date by which it must be passed, and what happens if it is not. When those terms are written down, both the commission and the supplier know what acceptance means. When they are left open, acceptance becomes a negotiation held under time pressure, a few weeks before polling day.
The commission should accept a system only after it has seen it fail, recover and still produce results that match the paper.
A full rehearsal, or mock election, run across the country under realistic conditions, brings all six tests together. It is also the moment when staff at every level find out what their part of the night will feel like. Plan it early enough that there is time to fix what it reveals.
Preparing a results system for acceptance? Write to us.
Election Technology, Digital ID & Digital Public Infrastructure